The graphs show the cumulative outputs achieved up to the present (the 3rd quarter of the current financial year 2006-7).
The target set for the overall project is shown in each case by a red line, and it is clear that the targets have been met already in the case of numbers of jobs created, new businesses created and businesses assisted with skills needs. The project is on course to achieve its target for learning opportunities. Whilst cumulative public investment is on track, private investment has far exceeded the target. The amount of new or refurbished floorspace is also very high.